ORDER NUMBER
G-29-23
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
Pacific Northern Gas Ltd. and Pacific Northern Gas (N.E.) Ltd.
Request to Amend Reporting Deadline to Submit Update on Gas Supply Options
Variance to Order G-265-20
BEFORE:
B. A. Magnan, Commissioner
on February 13, 2023
ORDER
WHEREAS:
A. By letter dated February 8, 2023, Pacific Northern Gas Ltd. (PNG-West) and Pacific Northern Gas (N.E.) Ltd. (PNG (NE)) (collectively, PNG), requests that the due date for filing its compliance filing related to British Columbia Utilities Commission (BCUC) Order G-265-20, be amended from December 31, 2022, to March 31, 2023 (Application);
C. The BCUC has reviewed the Application and determines that a variation of Order G-265-20 is warranted.
NOW THEREFORE pursuant to section 99 of the Utilities Commission Act, the BCUC orders as follows:
The Directive contained in the Decision accompanying Order G-265-20 is varied as follows:
1. The Panel finds that PNG has not fulfilled this directive in Order G-140-14 and directs PNG to file an update on all gas supply options and an examination of the merits of these options by March 31, 2023.
DATED at the City of Vancouver, in the Province of British Columbia, this 13th day of February 2023.
BY ORDER
Original signed by:
B. A. Magnan
Commissioner