ORDER NUMBER
G-82-23
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
British Columbia Hydro and Power Authority
Request to Remove the General Service E-Plus Rate
from the Electric Tariff, Effective April 1, 2023
BEFORE:
B. A. Magnan, Commissioner
on April 13, 2023
ORDER
WHEREAS:
A. On March 29, 2023, British Columbia Hydro and Power Authority (BC Hydro) requested to remove the General Service E-Plus rate from its Electric Tariff, effective April 1, 2023 (Application);
C. On April 20, 2020, the BCUC issued Order G-76-20, approving the amendments to RS 1205, 1206 and 1207 General Service – Dual Fuel (Closed) (General Service E-Plus), as filed in the application, effective the date of the order; and
D. The BCUC has reviewed the Application and determines that removing the General Service E-Plus rate from its Electric Tariff, thus rescinding RS 1205, 1206, and 1207, is warranted.
NOW THEREFORE pursuant to section 61 of the Utilities Commission Act, the British Columbia Utilities Commission orders as follows:
1. RS 1205, 1206, and 1207 are rescinded, effective April 1, 2023.
2. Tariff pages as filed in Attachment 1 of the application are accepted for filing.
DATED at the City of Vancouver, in the Province of British Columbia, this 13th day of April 2023.
BY ORDER
Original signed by:
B. A. Magnan
Commissioner