ORDER NUMBER

G-92-23

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Lake Okanagan Resort

Electrical Distribution Assessment Report

 

BEFORE:

B. A. Magnan, Panel Chair

E. B. Lockhart, Commissioner

A. Pape-Salmon, Commissioner

on April 21, 2023

 

ORDER

WHEREAS:

 

A.      On December 7, 2022, Lake Okanagan Resort (LOR) filed with the British Columbia Utilities Commission (BCUC) its Electrical Distribution Assessment Report (LOR Assessment Report) prepared by Falcon Engineering;

B.      By Order G-41-23 (Order) dated March 1, 2023, the BCUC established a public hearing process and a regulatory timetable for the review of the LOR Assessment Report (Hearing). In the Order, the BCUC directed LOR to provide notice of the Hearing to its customers; provide confirmation of compliance with notice requirements; provide proof of notice to the BCUC; submit a plan to the BCUC addressing the LOR Assessment Report, with further process to be determined at a later date;

C.      On March 29, 2023, LOR filed a request to extend the regulatory timetable, citing that due to a clerical error, it was unable to meet the deadlines outlined in the Order (Extension Request);

D.      By Order G-71-23 dated March 31, 2023, the BCUC accepted the Extension Request and amended the regulatory timetable;

E.       The BCUC has not received confirmation of compliance with notice requirements or proof of notice from LOR as set out in the regulatory timetable in Order G-71-23; and

F.       The BCUC considers an amendment to the regulatory timetable is warranted such that further process will be established after the April 27, 2023 deadline when LOR is required to submit a plan addressing the LOR Assessment Report to the BCUC.

 

 

NOW THEREFORE the BCUC orders an amended regulatory timetable is established as outlined in Appendix A to this order.

 

DATED at the City of Vancouver, in the Province of British Columbia, this                  21st                day of April 2023.

 

BY ORDER

 

Original signed by:

 

B. A. Magnan

Commissioner

 

 

Attachment

 

 


Lake Okanagan Resort

Electrical Distribution Assessment Report

REGULATORY TIMETABLE

 

 

Action

Date (2023)

LOR to submit plan addressing LOR Assessment Report to the BCUC

Thursday, April 27

Further Process

TBD

 