ORDER NUMBER
G-118-23
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
British Columbia Hydro and Power Authority
Request to Amend Major Capital Project Filing Guidelines
BEFORE:
A. K. Fung, KC, Panel Chair
A. C. Dennier, Commissioner
W. M. Everett, KC, Commissioner
on May 17, 2023
ORDER
WHEREAS:
A. On March, 17, 2023, British Columbia Hydro and Power Authority (BC Hydro) filed an application with the British Columbia Utilities Commission (BCUC) to request to amend the major capital project filing guidelines (Application);
B. On December 2, 2019, by Order G-313-19, the BCUC approved the 2018 Major Capital Project Filing Guidelines (2018 Guidelines), including BC Hydro’s commitment to submit applications to the BCUC for major capital projects with authorized cost estimates that exceed the following thresholds:
1. $100 million for Power System projects;
2. $50 million for Buildings projects; and
3. $20 million for Information Technology projects.
C. In the Application, BC Hydro seeks approval of:
i. An increase to the major capital filing thresholds, escalated annually by their respective price index for the previously completed calendar year, starting from fiscal 2019; and
ii. BCUC confirmation that a Certificate of Public Convenience and Necessity is not required for Customer IPID 901943 Project.
D. By Order G-113-23, dated May 9, 2023, the BCUC established a regulatory timetable for review of the Application;
E. On May 16, 2023, BC Hydro filed a request for an extension to the regulatory timetable; and
F. The BCUC has determined that an amendment to the regulatory timetable is warranted.
NOW THEREFORE the BCUC orders that the regulatory timetable is amended as set out in Appendix A to this order.
DATED at the City of Vancouver, in the Province of British Columbia, this 17th day of May 2023.
BY ORDER
Original signed by:
A.K. Fung, KC
Commissioner
Attachment
British Columbia Hydro and Power Authority
Request to Amend Major Capital Project Filing Guidelines
REGULATORY TIMETABLE
Action |
Date (2023) |
BC Hydro provides list of notified parties |
Wednesday, May 17 |
BC Hydro to submit further information |
Thursday, May 25 |
Submissions on BC Hydro’s Application* |
Thursday, June 1 |
BC Hydro reply submission |
Thursday, June 8 |
Further process |
To be determined |