ORDER NUMBER
G-122-23
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
Lake Okanagan Resort
Electrical Distribution Assessment Report
BEFORE:
B. A. Magnan, Panel Chair
E. B. Lockhart, Commissioner
A. Pape-Salmon, Commissioner
on May 30, 2023
ORDER
WHEREAS:
A. On December 7, 2022, Lake Okanagan Resort (LOR) filed with the British Columbia Utilities Commission (BCUC) its draft Electrical Distribution Assessment Report (LOR Assessment Report) prepared by Falcon Engineering;
B. By Order G-41-23 (Order) dated March 1, 2023, the BCUC established a public hearing process and a regulatory timetable for the review of the LOR Assessment Report (Hearing). In the Order, the BCUC directed LOR to provide notice of the Hearing to its customers; provide confirmation of compliance with notice requirements; provide proof of notice to the BCUC; submit a plan to the BCUC addressing the LOR Assessment Report, with further process to be determined at a later date;
C. By Orders G-71-23, dated March 31, 2023 and G-92-23 dated April 21, 2023, the BCUC amended the regulatory timetable;
D. On April 26, 2023, LOR submitted the final LOR Assessment Report and a plan addressing the LOR Assessment Report;
E. By letter dated May 25, 2023, the BCUC requested LOR to confirm its customers and customer addresses and received a confirmed list of customers from LOR on May 29, 2023; and
F. The BCUC has reviewed the information submitted by LOR and considers an amendment to the regulatory timetable is warranted.
NOW THEREFORE the BCUC establishes an amended regulatory timetable, as set out in Appendix A to this order.
DATED at the City of Vancouver, in the Province of British Columbia, this 30th day of May 2023.
BY ORDER
Original signed by:
B. A. Magnan
Commissioner
Attachment
Lake Okanagan Resort
Electrical Distribution Assessment Report
REGULATORY TIMETABLE
Action |
Date (2023) |
Deadline to submit Intervener Registration and Letters of Comment |
Wednesday, June 21 |
BCUC Information Request (IR) No. 1 |
Wednesday, June 28 |
Intervener IR No. 1 to LOR (if any) |
Wednesday, July 5 |
LOR Responses to BCUC and Intervener IR No. 1 and Letters of Comment (if any) |
Wednesday, July 12 |
Further Process |
TBD |