ORDER NUMBER
G-142-23
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
FortisBC Energy Inc.
Biomethane Energy Recovery Charge Rate Methodology and
Comprehensive Review of a Revised Renewable Gas Program
BEFORE:
D. M. Morton, Panel Chair
D. A. Cote, Commissioner
R. I. Mason, Commissioner
on June 14, 2023
ORDER
WHEREAS:
A. On December 17, 2021, in accordance with British Columbia Utilities Commission (BCUC) Orders G-35-21 and G-242-21, FortisBC Energy Inc. (FEI) filed its Stage 2 Comprehensive Review and Application for Approval of a Revised Renewable Gas Program (Application);
B. By Orders G-3-22, G-103-22, G-165-22A, G-28-23, G-86-23, and G-112-23 the BCUC established a regulatory timetable for review of the Application;
C. By letter dated May 8, 2023, FEI informed the BCUC that a matter (carbon tax matter) had arisen with respect to the Carbon Tax Act that may impact the evidence and approvals sought in the proceeding. FEI requested that the BCUC modify the regulatory timetable set by Order G-86-23, and allow FEI to file an update on the carbon tax matter by June 5, 2023, after which further process can be determined;
D. By letter dated June 5, 2023, in accordance with Order G-111-23, FEI provided an update regarding the carbon tax matter, and requested an amendment to the regulatory timetable to allow a further update regarding the carbon tax matter and a regulatory timetable proposal by August 1, 2023;
E. The BCUC has reviewed FEI’s request and determines that an amendment to the regulatory timetable is warranted.
NOW THEREFORE the BCUC orders as follows:
1. A further regulatory timetable is established, as set out in Appendix A to this order.
2. FEI is directed to provide a further update on the carbon tax matter and a regulatory timetable proposal by August 1, 2023. In its further update, FEI must also include an explanation of how FEI’s current biomethane program is affected by the carbon tax matter.
DATED at the City of Vancouver, in the Province of British Columbia, this 14th day of June 2023.
BY ORDER
Original signed by:
D. M. Morton
Commissioner
Attachment
FortisBC Energy Inc.
Biomethane Energy Recovery Charge Rate Methodology and
Comprehensive Review of a Revised Renewable Gas Program
REGULATORY TIMETABLE
Action |
Date (2023) |
FEI Update No. 2 on Carbon Tax Matter |
Tuesday, August 1 |
Further Process |
To be determined |