ORDER NUMBER

G-200-23

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

2021 Integrated Resource Plan

 

BEFORE:

D. M. Morton, Panel Chair

C. M. Brewer, Commissioner

T. A. Loski, Commissioner

R. I. Mason, Commissioner

 

on July 25, 2023

 

ORDER

WHEREAS:

 

A.      On December 21, 2021, British Columbia Hydro and Power Authority (BC Hydro) filed its 2021 Integrated Resource Plan (IRP) Application with the British Columbia Utilities Commission (BCUC), pursuant to section 44.1 of the Utilities Commission Act (UCA) and in accordance with Order G-28-21 dated January 27, 2021;

B.      By Order G-129-23 dated May 17, 2023, the BCUC established an amended regulatory timetable; and

C.      The BCUC determines that establishing an amended regulatory timetable is warranted.

NOW THEREFORE the BCUC orders as follows:

 

1.       An amended regulatory timetable is established as set out in Appendix A to this order.

 

2.       BC Hydro must provide a copy of this order and cover letter, within five business days of its issuance, electronically where possible, to all parties notified by BC Hydro in accordance with Order G-15-22.

DATED at the City of Vancouver, in the Province of British Columbia, this     25th    day of July 2023.

 

BY ORDER

 

Original signed by:

 

D. M. Morton

Commissioner

Attachment


British Columbia Hydro and Power Authority

2021 Integrated Resource Plan

 

REGULATORY TIMETABLE

 

BC Hydro’s Load Forecast Regulatory Process

 

ACTION

DATE (2023)

BC Hydro to Issue Public Notice of Change in Scope*

Thursday, August 3

Submissions on Regulatory Processes and Timetables from BC Hydro and Interveners

Thursday, August 3

Reply Submissions on Regulatory Processes and Timetables from
BC Hydro and Interveners

Thursday, August 10

BC Hydro Responses to Information Requests on Signposts Update

Friday, August 11

Late Intervener Registration Deadline

Friday, August 18

Updates to Intervener Evidence on Load Forecast Scenarios

Friday, August 25

Information Requests on Updated Intervener Evidence (on Load Forecast Scenarios only)

Friday, September 1

Responses to Information Requests on Updated Intervener Evidence (on Load Forecast Scenarios only)

Friday, September 8

BC Hydro Rebuttal Evidence (on Intervener Evidence on Load Forecast only)

Friday, September 15

Oral Hearing on BC Hydro’s Load Forecast Scenarios

Monday, September 25 and Tuesday, September 26 if required

Oral Hearing on Intervener Evidence (on Load Forecast only)

Thursday, October 12 and Friday, October 13, if required

Final Argument from BC Hydro on Load Forecast Scenarios

Thursday, October 26

Final Argument from Interveners on Load Forecast Scenarios

Thursday, November 23

Reply Argument from BC Hydro on Load Forecast Scenarios

Thursday, December 7

 

 

 

BC Hydro’s New Energy Acquisition Regulatory Process

 

ACTION

DATE (2023)

BC Hydro Workshop on Planned New Energy Acquisitions

Monday, October 16

Further Process on Planned New Energy Acquisitions

TBD

 

 

 

 