IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Boralex Ocean Falls Limited Partnership

Boralex Ocean Falls 2023 to 2027 Rates for Service to BC Hydro

 

BEFORE:

B.A. Magnan, Panel Chair

W.M. Everett, KC, Commissioner

 

on September 11, 2023

 

ORDER

WHEREAS:

 

A.      On April 28, 2023, Boralex Ocean Falls Limited Partnership (Boralex) applied to the British Columbia Utilities Commission (BCUC) for approval of permanent rates for service to British Columbia Hydro and Power Authority (BC Hydro) from January 1, 2023 to December 31, 2027, as outlined in the table below, and various deferral account approvals (Application);

B.      By Order G-342-22 the BCUC approved Boralex’s existing rates on an interim and refundable basis, effective January 1, 2023;

C.      By Order G-130-23 and G-214-23, respectively, the BCUC established and amended the regulatory timetable for the review of the Application; and

D.      The Panel has reviewed the evidence filed in the proceeding and considers that a further regulatory timetable is warranted.

 

 

 

 

NOW THEREFORE the BCUC furthers the regulatory timetable as set out in Appendix A to this order.

 

DATED at the City of Vancouver, in the Province of British Columbia, this           11th           day of September 2023.

 

BY ORDER

 

Original signed by:

 

B.A. Magnan

Commissioner

 

 

Attachment


Boralex Ocean Falls Limited Partnership

Boralex Ocean Falls 2023 to 2027 Rates for Service to BC Hydro

 

REGULATORY TIMETABLE

 

 

Action

Date (2023)

Boralex final argument, if any

Wednesday, September 27

Intervener final argument, if any

Wednesday, October 11

Boralex reply argument, if necessary

Wednesday, October 25

 