Orders

Decision Information

Decision Content

ORDER NUMBER

G-20-24

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

Application for a Certificate of Public Convenience and Necessity

for the Lower Mainland Reactive Power Reinforcement Project

 

BEFORE:

A. K. Fung, KC, Panel Chair

A. C. Dennier, Commissioner

 

on January 24, 2024

 

ORDER

 

WHEREAS:

 

A.      On November 22, 2022, British Columbia Hydro and Power Authority (BC Hydro) filed an application with the British Columbia Utilities Commission (BCUC) pursuant to section 45 and 46 of the Utilities Commission Act (UCA) seeking a Certificate of Public Convenience and Necessity (CPCN) for the Lower Mainland Reactive Power Reinforcement Project (Application);

B.      In the Application, BC Hydro proposes to install reactive power compensation equipment at the Meridian, Ingledow, McLellan and Clayburn substations and stop using the Burrard Synchronous Condenser Station to manage reactive power on BC Hydro’s transmission system; 

C.      On December 15, 2022, by Order G-363-22, the BCUC established a regulatory timetable for a review of the Application;

D.      BC Hydro filed the following exhibits on a confidential basis (Confidential Exhibits) during the proceeding:

         Exhibit B-1-1, BC Hydro submitting the Application including confidentially held Chapter 4 and Appendices F, G, H, J, K and L;

         Exhibit B-1-3, BC Hydro submitting confidential Application – Errata;

         Exhibit B-3-1, BC Hydro submitting responses to BCUC Request for Information including confidentially held attachments 1 to 8;

         Exhibit B-7-1, BC Hydro submitting confidential responses to BCUC IR No. 1;

         Exhibit B-8, BC Hydro submitting confidential responses to BCUC confidential IR No. 1;

         Exhibit B-9-1, BC Hydro submitting confidential responses to Intervener IR No. 1;

         Exhibit B-12-1, BC Hydro submitting confidential responses to BCUC IR No. 2;

         Exhibit B-13, BC Hydro submitting confidential responses to BCUC Confidential IR No. 2;

         Exhibit B-14-1, BC Hydro submitting confidential responses to Intervener IR No. 2; and

         BC Hydro submitting its confidential reply argument.

E.       By Orders G-8-23, G-127-23, G-173-23, G-208-23, and G-265-23 the BCUC established further and amended regulatory timetables, to include among other things, a BCUC workshop, two rounds of information requests, and final and reply arguments; and

F.       The BCUC has considered the evidence and submissions filed in this proceeding and makes the following determinations.

 

 

NOW THEREFORE for the reasons set out in the Decision issued concurrently with this order, the BCUC orders as follows:

 

1.       BC Hydro is denied a CPCN for the Lower Mainland Reactive Power Reinforcement Project.

2.       BC Hydro is directed to file within 90 days of the date of this decision, its contingency plan to manage the need for reactive power on its transmission system in the interim.

3.      The Confidential Exhibits shall be kept confidential until the BCUC determines otherwise.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this         24th         day of January 2024.

 

 

BY ORDER

 

Original signed by:

 

A. K. Fung, KC

Commissioner

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.