July 18, 2024                                                                                                                                                                                                     

 

Sent via email                                                                                                                                                                        Letter L-20-24

 

Mr. Lloyd Jacobs

General Manager

FortisBC Alternative Energy Services Inc.

10th Floor, 1111 West Georgia Street

Vancouver, B.C. V6E 4M3

FAES.regulatory.affairs@fortisbc.com

 

 

Re:         FortisBC Alternative Energy Services Inc. – Oliver’s Landing November 2024 to October 2025 Annual Contracting Plan

 

Dear Mr. Jacobs:

 

On June 28, 2024, FortisBC Alternative Energy Services Inc. (FAES) submitted to the British Columbia Utilities Commission (BCUC), on a confidential basis, its Annual Contracting Plan for the Oliver’s Landing area for the period of November 2024 to October 2025 (2024/25 ACP). In its submission, FAES requests BCUC acceptance of the Oliver’s Landing 2024/25 ACP. The objectives for the Oliver’s Landing 2024/25 ACP are identified as follows:

 

1. To provide secure, reliable, and cost-effective supply in order to meet customer requirements; and

 

2. To reduce the impact of propane price volatility on customers’ propane rates in a cost-effective manner.

 

The BCUC has reviewed the FAES filing and accepts the Oliver’s Landing 2024/25 ACP.

 

A copy of FAES’s non-confidential Executive Summary for the 2024/25 ACP is attached and is available for public review. Exclusive of the non-confidential Executive Summary, the BCUC will keep the Oliver’s Landing 2024/25 ACP confidential, until the BCUC determines otherwise.

 

Sincerely,

 

Original signed by:

 

Patrick Wruck

Commission Secretary

 

DS/jm

Enclosure


A document with text on it

Description automatically generated

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.