ORDER NUMBER
G-309-24
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
Kyuquot Power Limited
Certificate of Public Convenience and Necessity
for the Capacity Upgrade Project
BEFORE:
M. Jaccard, Panel Chair
E. A. Brown, Commissioner
on November 22, 2024
ORDER
WHEREAS:
A. By Order G-207-24, dated August 2, 2024, the British Columbia Utilities Commission (BCUC) accepted Kyuquot Power Limited’s (KPL) Resource Assessment Report, as adjusted to include load from the Chamiss Bay camp, as being in the public interest;
B. On November 7, 2024, KPL filed an application with the BCUC for a Certificate of Public Convenience and Necessity (CPCN) pursuant to sections 45 and 46 of the Utilities Commission Act (UCA) for the Capacity Upgrade Project (Project) (Application);
C. The Project includes a service upgrade by British Columbia Hydro Power and Authority (BC Hydro) at the point of interconnection between the KPL and BC Hydro systems, including the installation of a new
single-phase recloser, and an upgrade to the KPL system including the installation of a new recloser and voltage regulator. The combined upgrades will increase system demand capacity from 550 kW to approximately 1123 kW;
D. In the Application, KPL states the works to be completed by BC Hydro are based on a budget quotation with an expiration date of December 23, 2024. KPL explains that if this date is not met, the budget quotation would be subject to review and amendment, potentially resulting in a higher quote; and
E. The BCUC has reviewed the Application and determines that the establishment of a public hearing process is warranted.
NOW THEREFORE the BCUC orders as follows:
1. A regulatory timetable for the review of the Application is established as set out in Appendix A to this order.
2. KPL is directed to provide a copy of the Application and this order on or before Tuesday, November 26, 2024, to all known affected or potentially affected parties.
3. KPL is directed to make the Application available on its website at https://kyuquotpower.com by Tuesday, November 26, 2024.
4. KPL is directed to provide the Public Notice in Appendix B to this order to all of its customers by Tuesday, November 26, 2024.
5. KPL is directed to provide written confirmation to the BCUC, by Monday, December 2, 2024, of compliance with directives 2, 3 and 4 of this order.
6. In accordance with the BCUC’s Rules of Practice and Procedure, any party wishing to comment on the Application is invited to submit a Letter of Comment by the date established in the regulatory timetable. Letters of Comment must be submitted by way of the Letter of Comment Form available on the BCUC’s website at https://www.bcuc.com/Forms/LetterOfComment.
DATED at the City of Vancouver, in the Province of British Columbia, this 22nd day of November 2024.
BY ORDER
Electronically signed by Mark Jaccard
M. Jaccard
Commissioner
Attachment
Kyuquot Power Limited
Certificate of Public Convenience and Necessity
for the Capacity Upgrade Project
REGULATORY TIMETABLE
Action |
Date (2024) |
KPL to publish notice of the Application |
Tuesday, November 26 |
BCUC Information Request (IR) No. 1 to KPL |
Thursday, November 28 |
KPL provides confirmation of compliance with |
Monday, December 2 |
KPL responses to BCUC IR No. 1 |
Thursday, December 5 |
Letters of comment deadline |
Monday, December 9 |
KPL response to letters of comment, if any |
Thursday, December 12 |
BCUC Decision |
Friday, December 20 |
Kyuquot Power Ltd. Capacity Upgrade Project
On November 7, 2024, Kyuquot Power Ltd. (KPL) filed an application for a Certificate of Public Convenience and Necessity for the Capacity Upgrade Project. The purpose of the project is to increase KPL system demand capacity from 550 kW to approximately 1123 kW through upgrades to the distribution system on both sides of the interconnection with BC Hydro at Oclucje.
Please visit the Proceeding webpage on bcuc.com under “Our Work” to learn more.
To participate in the proceeding, visit www.bcuc.com/get-involved.
GET INVOLVED • Submit a letter of comment • Subscribe to the proceeding
|
IMPORTANT DATES 1. Monday, December 9 – Deadline to submit a letter of comment to share your views, opinions, and insights on the application |
Subscribe to this Proceeding on bcuc.com under “Get Involved” to receive email notifications when public documents are added to the proceeding.
CONTACT INFORMATION |
|
428 Broughton Avenue Niagara Falls, ON L2E 3K6
E: gregsunnell@gmail.com
P: 604. 992.9860 |
Suite 410, 900 Howe Street Vancouver, BC V6Z 2N3
E: Commission.Secretary@bcuc.com
P: 604.660.4700 |