Orders

Decision Information

Decision Content

ORDER NUMBER

G-57-25

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Plateau Pipe Line Ltd.

Abandonment of Service as a Common Carrier

on the Northern Segment of the Western Pipeline System

 

BEFORE:

T. A. Loski, Panel Chair

E. A. Brown, Commissioner

B. A. Magnan, Commissioner

 

on March 4, 2025

 

ORDER

WHEREAS:

 

A.      On October 7, 2024, Plateau Pipe Line Ltd. (Plateau), a wholly-owned subsidiary of Pembina Pipeline Corporation and general partner of Pembina West Limited Partnership, filed an application (Application) with the British Columbia Utilities Commission (BCUC) for approval to abandon common carrier service on the northern segment (Northern Segment) of the western pipeline system (Western System) pursuant to sections 65 and 72(2) of the Utilities Commission Act;

B.      By Order G-262-24 dated October 18, 2024, the BCUC established a public hearing process and regulatory timetable to review the Application. Subsequently, by Orders G-301-24, G-332-24, and G-350-24 dated November 19, 2024, December 12, 2024, and December 20, 2024, respectively, the BCUC established further regulatory timetables, which included amongst other things, one round of information requests (IRs) with responses due by March 5, 2025;

C.      By letter dated March 4, 2025, Plateau requested a two-day extension to the deadline for filing IR responses;

D.      By letter dated March 4, 2025, Tidewater Midstream and Infrastructure Ltd. confirmed its support for Plateau’s request to extend the deadline for filing IR responses; and

E.       The BCUC considers establishment of an amended regulatory timetable is warranted.

 

NOW THEREFORE the BCUC amends the regulatory timetable established by Order G-350-24, as set out in Appendix A to this order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this       4th        day of March 2025.

 

BY ORDER

 

Electronically signed by Tom Loski

 

T. A. Loski

Commissioner

 

 

Attachment

 

 


Plateau Pipe Line Ltd.

Abandonment of Service as a Common Carrier

on the Northern Segment of the Western Pipeline System

 

REGULATORY TIMETABLE

 

 

Action

Date (2025)

Plateau and Tidewater responses to IR No. 1

Friday, March 7

Plateau final argument

Wednesday, March 19

Tidewater final argument

Wednesday, April 2

Plateau reply argument

Wednesday, April 9

 