Orders

Decision Information

Decision Content

 

ORDER NUMBER

G-91-25

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Creative Energy Vancouver Platforms Inc.

2025 Core Steam Revenue Requirements

 

BEFORE:

E. A. Brown, Panel Chair

A. C. Dennier, Commissioner

B. A. Magnan, Commissioner

 

on April 7, 2025

 

ORDER

WHEREAS:

 

A.      On December 18, 2024, Creative Energy Vancouver Platforms Inc. (Creative Energy) filed with the British Columbia Utilities Commission (BCUC) its 2025 Revenue Requirements Application (RRA) for the thermal energy system serving downtown Vancouver, Northeast False Creek (NEFC), and the Butterfly Development (together, Core TES) (Application), seeking interim and permanent approval of rates, effective January 1, 2025;

B.      By Order G-11-25, the BCUC approved on an interim and refundable/recoverable basis, effective January 1, 2025, thermal energy service rates for the Core TES and established a regulatory timetable for the review of the Application, which included intervener registration, one round of information requests (IR) and final and reply arguments;

C.      On March 24, 2025, Creative Energy filed its responses to IR No. 1; and

D.      The BCUC has reviewed the evidentiary record and determines that amending the regulatory timetable to allow for Panel IRs is warranted.

 

NOW THEREFORE the BCUC amends the regulatory timetable established by Order G-11-25, as set out Appendix A to this order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this          7th          day of April 2025.

 

BY ORDER

 

Electronically signed by Elizabeth A. (Lisa) Brown

 

E. A. Brown

Commissioner

 

 

 

 


Creative Energy Vancouver Platforms Inc.

2025 Core Steam Revenue Requirements

 

REGULATORY TIMETABLE

 

 

Action

Date (2025)

Panel Information Request (IR) No. 1 to Creative Energy

Wednesday, April 9

Creative Energy responses to Panel IR No. 1

Wednesday, April 16

Creative Energy final argument

Wednesday, April 23

Intervener final argument

Monday, May 5

Creative Energy reply argument

Thursday, May 15

 

 