Orders

Decision Information

Decision Content

ORDER NUMBER

G-113-25

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Wyse Meter Solutions Inc.

Exemption under Section 88(3) of the UCA

 

BEFORE:

A. K. Fung, KC, Panel Chair

 

on May 1, 2025

 

ORDER

WHEREAS:

 

A.      On April 7, 2025, Wyse Meter Solutions Inc. (Wyse), filed an application (Application) with the British Columbia Utilities Commission (BCUC) pursuant to section 88(3) of the Utilities Commission Act (UCA) seeking approval to be exempted from the application of sections 50 to 54 of the UCA;

B.      By Order G-107-25 dated April 28, 2025, the BCUC established a regulatory timetable for review of the Application;

C.      On May 1, 2025, Wyse requested an extension to the deadline for providing notice of the Application from May 6, 2025, to May 20, 2025, to align with Wyse’s billing cycle and a corresponding extension to the other deadlines in the timetable; and

D.      The BCUC has reviewed the request and finds that an amendment to the regulatory timetable is warranted.

 

NOW THEREFORE the BCUC orders as follows:

 

1.       An amended regulatory timetable is established, as set out in Appendix A to this order.

2.       Wyse is directed to publish the Application and a copy of this order on its website at: www.wysemeter.com by Tuesday, May 20, 2025. The postings must remain in place until a final determination on the Application has been issued.

3.       Wyse is directed to provide notice of the Application and a copy of this order, electronically where possible, to all customers of Wyse located in BC and to the registered interveners in Wyse’s Submetering Systems and Rates for Service proceeding by Tuesday, May 20, 2025.

4.       Wyse is directed to provide written confirmation to the BCUC that it has posted a copy of the Application and this order on its website pursuant to Directive 2 and provided notice to interveners and its BC customers pursuant to Directive 3 by Thursday, May 22, 2025.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this       1st       day of May 2025.

 

BY ORDER

 

Electronically signed by Anna Fung

 

A. K. Fung, KC

Commissioner

 

 

Attachment


Wyse Meter Solutions Inc.

Exemption under Section 88(3) of the UCA

 

REGULATORY TIMETABLE

 

 

Action

Date (2025)

Wyse provides notice of Application

Tuesday, May 20

Wyse confirmation of compliance with notice requirements pursuant to Directive 4

Thursday, May 22

BCUC Information Request (IR) No. 1 to Wyse

Thursday, May 29

Wyse responses to BCUC IR No. 1

Monday, June 16

Letters of comment deadline

Tuesday, June 24

Wyse responses to letters of comment, if any, and final argument

Wednesday, July 2

 

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.