Orders

Decision Information

Decision Content

 

ORDER NUMBER

F-24-25

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Creative Energy Vancouver Platforms Inc.

2025 Core Steam Revenue Requirements

 

Participant Cost Award Application

 

BEFORE:

E. A. Brown, Panel Chair

A. C. Dennier, Commissioner

B. A. Magnan, Commissioner

 

on October 6, 2025

 

ORDER

WHEREAS:                                                                                                                                     

 

A.      On December 18, 2024, Creative Energy Vancouver Platforms Inc. (Creative Energy) filed with the British Columbia Utilities Commission (BCUC) its 2025 Revenue Requirements Application (RRA) for the Core thermal energy system (Application), which includes the steam distribution network and the Northeast False Creek and Butterfly Development hot water distribution networks;

B.      By Orders G-11-25 and G-91-25, dated January 23 and April 7, 2025, respectively, the BCUC established regulatory timetables for the review of the Application, which included public notice, intervener registration, one round of BCUC and intervener information requests (IR), one round of Panel IRs, and final and reply arguments;

C.      British Columbia Old Age Pensioners’ Organization, Active Support Against Poverty, Disability Alliance BC, Council of Senior Citizens’ Organizations of BC, and Tenant Resource and Advisory Center (BCOAPO), the Commercial Energy Consumers Association of British Columbia (the CEC), and Residential Consumer Intervener Association (RCIA) participated as interveners in the proceeding;

D.      By Order G-199-25A and the accompanying decision dated September 5, 2025, the BCUC issued its final decision on the 2025 RRA;

E.       The following participants filed Participant Cost Award (PCA) applications with the BCUC with respect to their participation in the proceeding:


 

Date

Participant

Application

May 27, 2025

RCIA

$13,979.44

August 13, 2025

The CEC

$18,460.65

August 20, 2025

BCOAPO

$20,873.45

 

F.       Creative Energy found the PCA applications reasonable; and

G.      The BCUC has reviewed the PCA applications in accordance with the criteria and rates set out in the BCUC Rules of Practice and Procedure and determines that the PCA applications should be approved.

 

NOW THEREFORE pursuant to section 118 of the Utilities Commission Act, the BCUC orders as follows:

 

1.       Costs are awarded to the following participants in the listed amounts for their participation in the 2025 Core Steam RRA proceeding:

Participant

Award

RCIA

$13,979.44

The CEC

$18,460.65

BCOAPO

$20,873.45

 

2.       Creative Energy is directed to reimburse the above-noted participants for the awarded amounts in a timely manner.

 

DATED at the City of Vancouver, in the Province of British Columbia, this            6th            day of October 2025.

 

BY ORDER

 

Electronically signed by Elizabeth A. (Lisa) Brown

 

E. A. Brown

Commissioner

 

 

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.