ORDER NUMBER

G-2-21

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Kyuquot Power Ltd.

Revenue Requirements Application

 

BEFORE:

K. A. Keilty, Panel Chair

 

on January 5, 2021

 

ORDER

WHEREAS:

 

A.      On November 30, 2020, Kyuquot Power Ltd. (KPL) filed an application with the British Columbia Utilities Commission (BCUC) for approval of amendments to its revenue requirements along with certain rate matters (Application);

B.      In the Application, KPL requests approval for the following:

1.       Confirmation of utility financials including rate base, depreciation rates, debt rate, return on equity and related items;

2.       The establishment of a new asset category named Deferred Depreciation Asset;

3.       The setting of an annual amortization of the Deferred Depreciation Asset in a fixed dollar amount;

4.       The establishment of a new asset category named Long Term Maintenance Asset (LTM);

5.       The setting of an annual depreciation rate on the LTM Asset of 25 percent straight-line;

6.       An increase of $1.00 per month to the Basic Charge under rate schedules 1101 and 1102; and

7.       An increase of $0.0272 per kWh to the Energy Charge under rate schedule 1102;

C.      The BCUC has commenced review of the Application and considers that establishing a regulatory timetable is warranted.

 

NOW THEREFORE the BCUC orders as follows:

 

1.       The regulatory timetable for the review of the Application is established, as set out in Appendix A to this order.

2.       KPL is directed to provide notice of the Application attached as Appendix B to this order, and this order, to all customers directly, either electronically or by mail, by Friday, January 29, 2021.

3.       Any party wishing to provide comments on the Application is invited to submit a letter of comment by Thursday, March 25, 2021. Letters of comment must be in the Letter of Comment Form available on the BCUC’s website at https://www.bcuc.com/forms/letter-of-comment.aspx, and submitted by email to commission.secretary@bcuc.com or by mail, to the BCUC, Suite 410, 900 Howe Street, Vancouver, BC,
V6Z 2N3
.

DATED at the City of Vancouver, in the Province of British Columbia, this      5th        day of January 2021.

 

BY ORDER

 

Original signed by:

 

K. A. Keilty

Commissioner

 

 

Attachment

 

 


Kyuquot Power Ltd.

Revenue Requirements Application

 

REGULATORY TIMETABLE

 

 

Action

Date (2021)

KPL Public Notice of Application

Friday, January 29

BCUC Information Request (IR) No. 1

Friday, February 26

KPL response to BCUC IR No. 1

Thursday, March 18

Deadline to submit Letters of Comment on KPL’s Application

Thursday, March 25

Further Process

To be determined

 

 


We want to hear from you

]

 


KYUQUOT POWER LTD. REVENUE REQUIREMENTS APPLICATION

On November 30, 2020, Kyuquot Power Ltd. (KPL) filed an application with the British Columbia Utilities Commission (BCUC) for approval of amendments to its revenue requirements along with certain rate matters (Application). In the Application, KPL is requesting changes to the Basic Charge and Energy Charge, along with other related matters.

 

 


HOW TO PARTICIPATE

         Submit a letter of comment

IMPORTANT DATE

             Thursday, March 25, 2021 – Submit a Letter of Comment to provide feedback on the Application

For more information on getting involved, please visit our website (www.bcuc.com/get-involved) or contact us at the information below.

 

GET MORE INFORMATION

 

Kyuquot Power Ltd.

100-1444 Alberni Street

Vancouver, BC  V6G 2Z4

 

E: tdeangelis@synex.com

 

P: 604.688.8271

British Columbia Utilities Commission

Suite 410, 900 Howe Street

Vancouver, BC Canada  V6Z 2N3

 

E: Commission.Secretary@bcuc.com

 

P: 604.660.4700

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.